Phase1 renovations progress

Installation of the fire suppression sprinkler system was completed a week ago in the basement.  Hoito was shutdown for a total of four days.  At the same time, accessibility improvements were done in the washrooms and a new support wall was constructed in preparation for the upcoming main floor elevator.  Ceiling tiles in the restaurant and kitchen were also replaced.

The small building addition on the Algoma side is coming along nicely.  It will contain the entrance to the street level elevator which will service the basement and the main floor.